- 9 out of the 11 required wells for First Oil are now complete.
- 92% work completion of construction of the well pads and infield roads.
- 95% of the operational support infrastructure is ready. This includes; the Supply Base, permanent camp, and safety station. These are key to ensure smooth operations when oil production commences.
- 40% completion of construction of key units namely the Central Processing Facility (CPF), lake water intake station and flow lines.
- 84% completion of construction of the 48 km kingfisher feederline and 66kV powerline to extend the grid to the Kingfisher Project Area.