- Land acquisition for the 2,901-acre site is nearly complete, with 100% of affected individuals compensated.
- So far, 64 out of 426 planned wells have been drilled, with successful hydrocarbon findings in targeted reservoirs.
- 99% completion of civil works for the Tilenga Project Area with all sections handed over to relevant contractors
- Steel and formwork for the main oil storage tank foundations have been completed at the Central Processing Facility (CPF) site.
- The CPF construction is ongoing with pipe racks being erected and equipment foundations being constructed.